UNIVERSITY OF SHEFFIELD | BARTOLOME HOUSE RAILING REPLACEMENT & RETAINING WALL RECONSTRUCTION
BARTOLOME HOUSE
UNIVERSITY OF SHEFFIELD
LISTED ROOF RAILING REPLACEMENT
LISTED RETAINING WALL RECONSTRUCTION
PRINCIPAL CONTRACTOR
£1.5m
49 Weeks
JCT INTERMEDIATE BUILDING CONTRACT WITH CONTRACTORS DESIGN
RAILING REPLACEMENT
ASSIX were appointed to complete the removal and replacement of heritage rooftop railings at Bartolome House. The existing cast-iron railings were an important feature of the building but due to their age required replacement. ASSIX worked with a specialist fabricator to supply and install 260 meters of replica aluminium railings to be an exact match to the existing style and patterns. This included taking and preparing samples for approval with the heritage officer.
Enabling works were also required to ensure the new railings would be suitably fixed and secured at roof level and to weatherproof all fixings. An extensive scheme of masonry remedial works was also carried out at the eaves and parapet level during the project while scaffolding was in place.
Associated works to provide improved roof access routes and replace access doors were also carried out as well as extensive timber sash window repairs.
In summary, the works included the following activities:
Railing removal and labelling.
Casting samples for approval.
Design and erection of access scaffold and providing hoisting.
Phased works across each wing of the building.
Preparation of existing fixings points for new railings.
Installation of new aluminium railings.
Weathering details to railings and backstay.
Lightning Protection works.
Roof access routes.
Roof access door replacements.
Masonry repairs including stone repairs, reporting, chimney repairs.
Timber sash window & glazing repairs.
Decorations to railings, windows and other external features.
RETAINING WALL RECONSTRUCTION
ASSIX were also awarded the concurrent works at Bartolome House to complete the demolition and reconstruction of a listed brick retaining wall to the front of the building. The first operation ASSIX completed was the installation of a designed scaffold shoring system to prevent further risk from the wall collapsing. This involved a complex traffic management requirement and liaison with the local authority.
As the wall was listed ASSIX carried out a detailed survey of all features and carefully carried out the demolition works, labelling and sorting all bricks and stonework for reinstallation. The demolition works also required the design and installation of temporary works to support the retained elements of the wall. This involved liaising with the adjacent properties to agree the works as well as enabling works to prepare suitable ground and subsequent making good on completion.
The new retaining wall was to be formed in reinforced concrete with a new foundation and RC wall to support the masonry face. Working in a confined area between the building and footpath ASSIX managed a logistically complete phased process to complete the casting of the new wall while working around existing below ground services and altering drainage.
In summary, the works included the following activities:
Design, installation and logistics for install of temporary shoring to wall.
Survey and document wall dimensions and details for replication.
Carefully demolish the wall including labelling and storage of brickwork for re-use.
Sourcing acceptable replacement masonry items where the existing were unable to be reused.
Installation of temporary works to support the retained sections of the wall.
Phased excavation and demolition.
Protection of existing services and installation of new ducting.
Drainage alterations.
Casting new RC foundations & retaining wall.
Reconstruction of masonry facing the wall including copings etc.
Asphalt surfacing works to the rear of the wall and to the adopted footpath.
Replacement of railings affected by the works.
Replacement of yorkstone steps and copings.
New metal fencing.
Access and traffic management throughout the works with the building remaining open for use.
Assix are pleased to have successfully carried out this complex project for the University of Sheffield. We look forward to continuing our relationship with the University and its project management teams.
Assix were appointed as Principal Contractor on this two-phased listed building refurbishment project.
Assix were appointed as Principal Contractor for the refurbishment of levels 0 - 4 of the DICe Building which is located on Clarendon Street, Nottingham within the NTU City Campus.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2024
Working alongside the University of Sheffield to preserve and restore this important local landmark has been a tremendous privilege for ASSIX.
Assix were appointed as Principal Contractor for the refurbishment of Level 6 at the Western Bank Library building at the heart of the University Campus
Assix were appointed as Principal Contractor to complete this extensive facade refurbishment project for the University of Sheffield at their hexagonal Geography Building.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2023
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2022
Assix were appointed as Principal Contractor to complete a project of cast-iron heritage railing replacements and reconstruction of a listed retaining wall at Bartolome House.
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor following a competitive tender process to construct a new locker building for Derbyshire Police within the grounds of Ripley Police Station.
Assix were appointed as Principal Contractor to complete a large re-roofing project for the University of Sheffield at the Hadfield CBE Building. The complex works involved detailed phasing to maintain critical plant services within the building while facilitating the works.
Assix were appointed as Principal Contractor following a competitive tender process to carry out re-roofing to the Broad Lane Block housing the University’s Civil and Structural Engineering Department. The works were carried out above and within live teaching environments which required meticulously planned operations to complete the works safely and with minimal disruption. £600,000 project completed over 16 weeks.
Assix provided a full Construction Management service on this £325k car park extension & reconfiguration project for Univar & Ventgrove. The works in Bradford comprised extensive surface water drainage alongside new surfacing and electric vehicle charging point provision.
Assix completed Pre-Construction & Enabling Works Management Role for this £10m New Build Residential Project. Including development of project cost plan, programme & management of demolition and site remediation works.
Assix carefully delivered this office refurbishment project for an international chemical distributer in Wilmslow, Manchester.
Shell & Core Refurbishment of an 8 storey, 37,000 sq/ft city centre office building. Including roof repair, window refurbishment and concrete facade repairs.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
Assix provided sub-contractor support services to take London Underground brief and translate into safe and workable solution in rail workshop environement.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
The installation of a single storey double gable extension to provide new kitchen and garden room with existing kitchen and dining room subject to refurbishment to open up existing space and create a large dining and entertaining area