UNIVERSITY OF SHEFFIELD | TEACHING SPACES 2023
TEACHING SPACES 2023
UNIVERSITY OF SHEFFIELD
PRINCIPAL CONTRACTOR
£600k
27 WEEKS
JCT INTERMEDIATE WITH CONTRACTORS DESIGN
TEACHING SPACES REFURBISHMENT
ASSIX were appointed after a successful tender for the strip out, installation, decoration and make-good of various existing components of chosen teaching and learning spaces within designated buildings owned and used by the University of Sheffield. The project included renovation of the Tapestry Room which is the executive meeting room for the University’s chancellors.
The works were completed concurrently across 19 teaching areas within 5 separate buildings including the Grade II Listed Firth Court. The buildings continued to be occupied during the renovations with ASSIX required to manage the shared access & material handling routes to avoid disruption and ensure safety.
The project required coordination with multiple stakeholders including the Audio Visual specialist & IT teams to ensure equipment deliveries were achieved on time. The project was also subject to late changes as the extent of the work often required investigation before designs could be finalised. This was particularly the case for the refurbishment of lecture theatres following asbestos abatement works.
Scope of Works:
Strip out of existing containment, electrical, data and AV installations in multiple areas
New electrical, data and AV service installations inc lighting replacement and fire alarm works
Partitions and plastering
Screed installation
Making good existing walls, decorations throughout and replacement of floor finishes (including vinyl, carpet/refinishing of existing timber parquet flooring)
Fire stopping
Joinery including construction of new lecture theatre staging, fire escape staircases and joisted flooring
Removal of existing seating, reupholstery/installation of lecture theatre seating
Installation of acoustic wall panels/ceiling rafts
Installation of new suspended ceilings/replacement tiles
Installation of door automation/access control equipment
Transferable Knowledge & Key Lessons Learnt:
Importance of highlighting required changes to M&E design based on constraints and limitations of building structure and existing service distribution routes
Working in consideration of existing building occupants and accommodating safe continued use of adjacent educational spaces
Works spread over an increased number of multiple work areas vs 2022 project required close co-ordination of subcontractors to ensure programme handover dates were maintained or subject to betterment when compared with room booking dates to smooth project delivery and hand back of areas for University use.
COMPLETION PHOTOS
Assix were appointed as Principal Contractor on this two-phased listed building refurbishment project.
Assix were appointed as Principal Contractor for the refurbishment of levels 0 - 4 of the DICe Building which is located on Clarendon Street, Nottingham within the NTU City Campus.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2024
Working alongside the University of Sheffield to preserve and restore this important local landmark has been a tremendous privilege for ASSIX.
Assix were appointed as Principal Contractor for the refurbishment of Level 6 at the Western Bank Library building at the heart of the University Campus
Assix were appointed as Principal Contractor to complete this extensive facade refurbishment project for the University of Sheffield at their hexagonal Geography Building.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2023
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2022
Assix were appointed as Principal Contractor to complete a project of cast-iron heritage railing replacements and reconstruction of a listed retaining wall at Bartolome House.
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor following a competitive tender process to construct a new locker building for Derbyshire Police within the grounds of Ripley Police Station.
Assix were appointed as Principal Contractor to complete a large re-roofing project for the University of Sheffield at the Hadfield CBE Building. The complex works involved detailed phasing to maintain critical plant services within the building while facilitating the works.
Assix were appointed as Principal Contractor following a competitive tender process to carry out re-roofing to the Broad Lane Block housing the University’s Civil and Structural Engineering Department. The works were carried out above and within live teaching environments which required meticulously planned operations to complete the works safely and with minimal disruption. £600,000 project completed over 16 weeks.
Assix provided a full Construction Management service on this £325k car park extension & reconfiguration project for Univar & Ventgrove. The works in Bradford comprised extensive surface water drainage alongside new surfacing and electric vehicle charging point provision.
Assix completed Pre-Construction & Enabling Works Management Role for this £10m New Build Residential Project. Including development of project cost plan, programme & management of demolition and site remediation works.
Assix carefully delivered this office refurbishment project for an international chemical distributer in Wilmslow, Manchester.
Shell & Core Refurbishment of an 8 storey, 37,000 sq/ft city centre office building. Including roof repair, window refurbishment and concrete facade repairs.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
Assix provided sub-contractor support services to take London Underground brief and translate into safe and workable solution in rail workshop environement.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
The installation of a single storey double gable extension to provide new kitchen and garden room with existing kitchen and dining room subject to refurbishment to open up existing space and create a large dining and entertaining area