UNIVERSITY OF SHEFFIELD | BARTOLOME HOUSE ROOFLIGHTS
BARTOLOME HOUSE
UNIVERSITY OF SHEFFIELD
ROOFLIGHT REPLACEMENTS
PRINCIPAL CONTRACTOR
£1,000,000
12 Weeks
JCT INTERMEDIATE BUILDING CONTRACT WITH CONTRACTORS DESIGN
ROOFLIGHT REPLACEMENT
ASSIX completed works to replace three large rooflights over atriums & corridors at Bartolome House for the University of Sheffield. This 16-week project included the design and installation of replacement aluminium rooflights to the existing openings and upstands as well as associated mechanical plant relocations and providing new AHU units.
The works were carried out above occupied spaces and therefore the installation of weather tents above the openings and crash decks internally was a critical part of the process to avoid water ingress. As part of this building is listed it was not possible to fix into some of the building structures resulting in alternative scaffold design solutions being identified and installed.
An extensive survey and design process was completed to ensure the rooflights would be a perfect fit to the existing openings and support steelworks. The works revealed some challenges with existing guttering structures and details which were required to be removed and re-built to provide structural support.
Two new air handling units were to be installed along with associated ductwork and BMS relocations at roof level and internally. This involved crane lifts being planned in and sequenced for the works while managing the maximum load capacity of the roof and materials storage.
Internally alterations were made to walls and fire stopping was carried out along with redecorations after installation of the rooflights.
During the project, ASSIX were awarded works to repoint areas of the external walls of the building and carry out stone repairs all to listed building elements. ASSIX also provided emergency shoring to a retaining wall at risk of collapse, safely managing the installation of propping and traffic management to a busy main road while the remedial works could be planned.
In summary, the works included the following:
Erection of scaffold access, weather tents and crash decks.
Strip out of existing rooflights and disposal from the site.
Mechanical & Electrical services disconnections, relocations and removals to facilitate the works including BMS.
Remove and rebuild bespoke accessible guttering detail around large roof light including liquid applied coating.
Joinery work to prepare upstands for fixing points of the new rooflights.
Installation of new aluminium rooflights to existing openings.
Flashings and weatherproofing work.
Internally complete electrical and BMS works and fire stopping to make good.
Carry out decorations to affected areas.
Complete cleaning of existing atrium glazing.
Replace roof lights actuators for ventilation.
Repointing to the listed wall at boundary of the site including access and traffic management.
Stone repairs to window openings and copings on a listed building.
Manage installation of emergency shoring to retaining wall at risk of collapse.
Traffic management to the works on the busy main road including out of hours road closures.
Specialist structural monitoring equipment to detect movement in the wall during works.
Assix are pleased to have successfully carried out this complex project for the University of Sheffield. We look forward to continuing our relationship with the University and their project management teams.
Assix were appointed as Principal Contractor on this two-phased listed building refurbishment project.
Assix were appointed as Principal Contractor for the refurbishment of levels 0 - 4 of the DICe Building which is located on Clarendon Street, Nottingham within the NTU City Campus.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2024
Working alongside the University of Sheffield to preserve and restore this important local landmark has been a tremendous privilege for ASSIX.
Assix were appointed as Principal Contractor for the refurbishment of Level 6 at the Western Bank Library building at the heart of the University Campus
Assix were appointed as Principal Contractor to complete this extensive facade refurbishment project for the University of Sheffield at their hexagonal Geography Building.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2023
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2022
Assix were appointed as Principal Contractor to complete a project of cast-iron heritage railing replacements and reconstruction of a listed retaining wall at Bartolome House.
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor following a competitive tender process to construct a new locker building for Derbyshire Police within the grounds of Ripley Police Station.
Assix were appointed as Principal Contractor to complete a large re-roofing project for the University of Sheffield at the Hadfield CBE Building. The complex works involved detailed phasing to maintain critical plant services within the building while facilitating the works.
Assix were appointed as Principal Contractor following a competitive tender process to carry out re-roofing to the Broad Lane Block housing the University’s Civil and Structural Engineering Department. The works were carried out above and within live teaching environments which required meticulously planned operations to complete the works safely and with minimal disruption. £600,000 project completed over 16 weeks.
Assix provided a full Construction Management service on this £325k car park extension & reconfiguration project for Univar & Ventgrove. The works in Bradford comprised extensive surface water drainage alongside new surfacing and electric vehicle charging point provision.
Assix completed Pre-Construction & Enabling Works Management Role for this £10m New Build Residential Project. Including development of project cost plan, programme & management of demolition and site remediation works.
Assix carefully delivered this office refurbishment project for an international chemical distributer in Wilmslow, Manchester.
Shell & Core Refurbishment of an 8 storey, 37,000 sq/ft city centre office building. Including roof repair, window refurbishment and concrete facade repairs.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
Assix provided sub-contractor support services to take London Underground brief and translate into safe and workable solution in rail workshop environement.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
The installation of a single storey double gable extension to provide new kitchen and garden room with existing kitchen and dining room subject to refurbishment to open up existing space and create a large dining and entertaining area