AQUARIUS HOUSE | BRADFORD
AQUARIUS HOUSE
CAR PARK EXTENSION & RECONFIGURATION CREATING 50+ NEW SPACES
COST PLANNING
PROCUREMENT
£325,000
10 Weeks
JCT CONSTRUCTION MANAGEMENT
CAR PARK EXTENSION
Assix provided Construction Management services from project inception to completion for this £325,000 project to extend and refurbish the existing car parking at this live office site. Assix prepared the project cost plan, risk register and programme of works during pre-construction and worked with the design team to achieve some £200k savings to the proposals. The client was also provided with expertise in mitigating a number of risks during pre-construction such as strategy for hot spots of contamination and working around underground services. The works were completed within programme and under cost plan with minimal disruption to the office facility.
PRE-CONSTRUCTION
Design team input to provide practical solutions and advise on risk during the works.
Preparation of project cost plan based on market pricing through Assix Supply Chain.
Logistics planning working with tenants and building managers to ensure minimal disruption during the project.
Project programme of works.
Pre-construction testing and surveys to remove and manage risks and provide cost certainty.
CONSTRUCTION STAGE - PROJECT & COST MANAGEMENT
Assix provided a complete Construction Management service during the construction phase.
Including procurement of all Trade Contractor works, drafting and issuing of contract documents.
Assix provided the Construction Phase H&S Plan and all relevant welfare and site safety equipment.
Ongoing management of site health and safety including auditing and reporting.
Contract Administration including valuation and certification of works.
Change control process keeping all parties in the loop.
Negotiation with Trade Contractors for variation works to achieve best value for the client.
Design co-ordination during the works including flagging of any matters identified on site and in the ground while working with the design team to implement the most efficient solutions.
Regular programme monitoring and reporting to the project team to ensure the project remained on track.
Handover of the works including commissioning, client training and O&M manuals.
SCOPE OF WORKS
Site clearance including vegetation, trees and fixtures.
Breaking out existing structures and surfaces.
Installation of new surface water drainage system including 75m3 attenuation tank, petrol interceptor and flow control valve.
Connection into existing drainage system.
Cut, fill and muck away to facilitate new areas of surfacing.
Gabion basket retaining walls.
New areas of interlocking block pavings.
New areas of asphalt surfacing.
New kerbs & edgings.
Topsoiling and planting of new trees.
Armco protection barriers.
Line Marking.
Relocation of external lighting columns.
Installation of new Electric Vehicle Charging Point.
Assix were appointed as Principal Contractor on this two-phased listed building refurbishment project.
Assix were appointed as Principal Contractor for the refurbishment of levels 0 - 4 of the DICe Building which is located on Clarendon Street, Nottingham within the NTU City Campus.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2024
Working alongside the University of Sheffield to preserve and restore this important local landmark has been a tremendous privilege for ASSIX.
Assix were appointed as Principal Contractor for the refurbishment of Level 6 at the Western Bank Library building at the heart of the University Campus
Assix were appointed as Principal Contractor to complete this extensive facade refurbishment project for the University of Sheffield at their hexagonal Geography Building.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2023
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor for the refurbishment of multiple teaching & learning spaces during the summer of 2022
Assix were appointed as Principal Contractor to complete a project of cast-iron heritage railing replacements and reconstruction of a listed retaining wall at Bartolome House.
Assix were appointed as Principal Contractor to complete the replacement of three large atrium rooflights for the University of Sheffield at the Hadfield CBE Building. The works were completed under the protection of weather tents while the building was occupied and involved extensive services works.
Assix were appointed as Principal Contractor following a competitive tender process to construct a new locker building for Derbyshire Police within the grounds of Ripley Police Station.
Assix were appointed as Principal Contractor to complete a large re-roofing project for the University of Sheffield at the Hadfield CBE Building. The complex works involved detailed phasing to maintain critical plant services within the building while facilitating the works.
Assix were appointed as Principal Contractor following a competitive tender process to carry out re-roofing to the Broad Lane Block housing the University’s Civil and Structural Engineering Department. The works were carried out above and within live teaching environments which required meticulously planned operations to complete the works safely and with minimal disruption. £600,000 project completed over 16 weeks.
Assix provided a full Construction Management service on this £325k car park extension & reconfiguration project for Univar & Ventgrove. The works in Bradford comprised extensive surface water drainage alongside new surfacing and electric vehicle charging point provision.
Assix completed Pre-Construction & Enabling Works Management Role for this £10m New Build Residential Project. Including development of project cost plan, programme & management of demolition and site remediation works.
Assix carefully delivered this office refurbishment project for an international chemical distributer in Wilmslow, Manchester.
Shell & Core Refurbishment of an 8 storey, 37,000 sq/ft city centre office building. Including roof repair, window refurbishment and concrete facade repairs.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
Assix provided sub-contractor support services to take London Underground brief and translate into safe and workable solution in rail workshop environement.
Assix provided sub-contractor support services to take the Network Rail brief and translate into safe and workable solution in a rail workshop environment. Assix also provided estimating, procurement and change control management.
The installation of a single storey double gable extension to provide new kitchen and garden room with existing kitchen and dining room subject to refurbishment to open up existing space and create a large dining and entertaining area